← All views

Company Brain

SIMULATION
STATUS DATEw/e 29 Nov 2026

The building, where it hurts

The same elevation, now live: markers show where the project is healthy, drifting, or held up. Click a marker to see the critical chain running through that point. A dashed ring means the cause is off-site (an order, a document, a signature).
Built In progress Planned on course · drifting · held up ◌ off-site cause

Drift, fever chart

Buffer consumed vs chain complete. Stay under the diagonal.

Open items

The chain and its shock absorber

Decisions waiting

The record, what the consultant sees

Baseline vs forecast against the contractual calendar. Milestones, notice windows, and today. This face never shows buffers.
Outward face ›Approved baseline: Rev 0 · unchangedProgramme updates: CPM format, monthly, on timeBuffers & chain stay internal.